Take a look at the progress for the last week of February 2021 at 85 Ben Fairless Drive.

85 Ben Fairless Drive Update Video

The latest update from 85 Ben Fairless Drive for the last week of February 2021 Sediment traps (basins) are excavated Underground civil work concluding
Storm-2700lf along with 60 structures and 2 tie-ins-complete
Sanitary-250lf-complete
Domestic Water- 100lf-complete
Fire Line-2700lf with 2 hydrants and 6 valves installed- 1 water vault-1 meter pit-complete
Infiltration basin-completing this week

NEXT PHASE
Start building the haul road Import fill material and bring up the pad to grade